AC Transit construction crews are currently working on installing new wheelchair accessible curb ramps, modern traffic signals, LED street light and other improvements along the 9.5-mile bus rapid transit (BRT) corridor.
DOWNTOWN OAKLAND — Broadway between 11th and 20th Streets
· Removing old concrete
· Underground utilities work
· Installing communications network
· Building BRT station
· Underground utilities work
· Installing traffic signal
· Building new sidewalk or curb ramp
CHINATOWN — 11th and 12th Streets, between Broadway and Lake Merritt Boulevard
· Removing old concrete
· Installing traffic signal
· Building new sidewalk or curb ramp
· Underground utilities work
· Installing communications network
· Building BRT stations
EASTLAKE — International Boulevard and East 12th Street, between Lake Merritt Boulevard/1st Avenue and 14th Avenue
· Building new sidewalk or curb ramp
· Removing old concrete
· Underground utilities work
· Installing traffic signal
· Installing communications network
· Building BRT stations
· Building new roadway
· Constructing center median
SAN ANTONIO — International Boulevard between 14th Avenue and 23rd Avenue
· Removing old concrete
· Building new sidewalk or curb ramp
· Underground utilities work
· Installing communications network
· Installing traffic signal
· Building BRT station
· Building new roadway
· Constructing center median
FRUITVALE — International Boulevard between 24th Avenue and 42nd Avenue
· Removing old concrete
· Building new sidewalk or curb ramp
· Installing communications network
· Underground utilities work
· Installing traffic signal
· Building new roadway
· Building BRT station
· Constructing center median
HAVENSCOURT-LOCKWOOD — International Boulevard between 42nd Avenue and 66th Avenue
· Installing communications network
· Building new sidewalk or curb ramp
· Installing traffic signal
· Underground utilities work
· Removing old concrete
HEGENBERGER — International Boulevard between 66th Avenue and 86th Avenue
· Major work completed; final elements coming later this year.
ELMHURST — International Boulevard between 86th Avenue and Durant Avenue
· Installing communications network
· Major work completed; final elements coming later this year.
SAN LEANDRO — East 14th Street from Durant Avenue to Davis Street, and Davis Street from East 14th Street to San Leandro Boulevard
· Installing communications network
· Building the San Leandro Transit Center
About AC Transit’s BRT
BRT is a $216 million investment in the community. BRT bus service mirrors the frequency, reliability and safety of light-rail train service without the high cost of building a rail line. BRT will operate along a 9.5-mile corridor between downtown Oakland and the San Leandro BART Station, primarily along International Boulevard and East 14th Street.