STM Blue Line extension Project Office issues tender for final phase of project
The Société de transport de Montréal’s (STM) Blue Line extension Project Office has issued the final call for tenders for the construction of a tunnel using a tunnel boring machine (TBM) and for site preparation work for some of the future stations and auxiliary structures, marking the largest contract to be awarded in the project.
Given the complexity of this contract, a two-stage call for tenders process was selected. In the first phase of the call for tenders, which began in December 2022, preliminary tenders were received. STM says the first phase had the benefit of beginning a discussion process with the pre-qualified bidders and provided specificity on the financial and technical aspects of the project.
The winning bidder will be announced in the first quarter of 2024. This bidder will be responsible for providing:
- The detailed design, supply and operation of the TBM
- The construction of the tunnel between Pie-IX and Anjou West using a TBM
- The construction of the tunnel between Pie-IX and the tail tracks of the current Blue line using conventional tunnelling methods
- The excavation of Pie-IX (main entrance building only), Viau and Lacordaire stations and some auxiliary structures
Updated project schedule
Following the discussion process with bidders, the timetable was extended to be fine-tuned around market realities. As a result, the Blue line extension will not be put into operation before 2030. The scenario for putting the line extension into operation will be confirmed when the next contracts have been awarded and the final terms of the project have been approved.
The project office still intends to begin major excavation work in 2024. The project is officially in its execution phase. Work is continuing as planned, in concert with the partners responsible for the project.