The project includes a 4.5-kilometer light-rail extension from Century Park to north of Ellerslie Road, two new stations and a light-rail vehicle storage and maintenance facility...
Signatories to the MOU included the city of Beaumont, town of Devon, city of Edmonton, city of Fort Saskatchewan, city of Leduc, Leduc County, Parkland County, city of Spruce ...
Phase 1 construction was originally anticipated to be complete in 2025 but was completed in December 2023, with the new NAIT/Blatchford Market LRT station opening for passenger...
The 8.1-mile system connects Mill Woods to downtown Edmonton via rail for the first time, stopping at 11 new neighborhood stops, with direct connections to multiple bus lines....
Both city officials and the contractor building the project expressed disappointment in the news and vowed to find a solution to deliver the line into safe operation.
Edmonton City Council approved and launched the Enhanced Transit Safety Plan in February 2022 to improve safety and accessibility for community members.
The Valley Line Southeast LRT is an integral part of achieving the city of Edmonton’s City Plan and will provide more accessible, convenient and sustainable travel options for...
The funding through The Alberta Transit System Cleanup Grant will support several city initiatives, including the renovation of two vacant cafes into work stations, as well as...
Train testing was briefly paused in June when TransEd identified signaling cables that needed to be replaced along the alignment to improve long-term system reliability.
The Community Outreach Transit Team brings together outreach workers from Bent Arrow Traditional Healing Society with Transit Peace Officers from the city of Edmonton to help ...