Headwall construction begins for Metrolinx’s Scarborough Subway Extension

April 13, 2022
It will take crews roughly four to six months to build each headwall, and work will also involve utility relocations.

Metrolinx crews are starting work on headwalls for Scarborough’s three-stop subway extension project. 

Headwalls are underground support structures made up of a series of concrete columns, called piles, that create a watertight wall around the area of future subway stations and emergency exit buildings. 

Construction is now underway for the first headwall just south of the launch shaft site at Sheppard Avenue East and McCowan Road. Similar to the ones installed at the launch shaft site last summer to prepare for excavation, piles will be drilled into the ground using large drill rigs, which are usually more than 33 meters (about 108 feet) high. 

Approximately 19 piles will be required for each headwall. 

“As the tunnel boring machine travels underground from the launch shaft site, it will bore through these headwalls, leaving behind the frames for stations and emergency exit buildings we’ll build later,” said Andrej Butala, headwall manager for the project. 

Crews will build headwalls at 12 sites along the project route. All of them must be built before the project’s tunnel boring machine, Diggy Scardust, arrives at each location. 

At each future station and emergency exit building site, crews will be installing a pair of headwalls to mark where the buildings will start and end. After the tunnel boring machine bores through these headwalls and tunnelling is completed, the successful stations, rail and systems (SRS) contractor will use the headwalls as frames to complete building the future stations and emergency exit buildings. 

The headwalls need to go deeper than the future tunnels to ensure that water and soil don’t disrupt the area during tunnelling or construction. 

Butala says each pile will be drilled roughly 40 meters (131 feet) underground and a single drill rig will be used at most sites to complete this work. 

It will take crews roughly four to six months to build each headwall, and work will also involve utility relocations. 

Metrolinx says it will take several steps to keep the community informed before starting construction at each location, including holding meetings, distributing notices and putting up signage. Community members can also sign up to receive construction updates through the project’s newsletter and can review current and past updates on Metrolinx’s website.