SFMTA eases T-Third bottleneck via 4th Street Bridge transit lanes

March 22, 2021
The transit lanes will be installed in a phase approach, depending on traffic delays.

The San Francisco Municipal Transportation Agency (SFMTA) Board of Directors approved temporary emergency transit lanes for the 4th Street Bridge to address a key bottleneck that delays the T Third line on the street northbound and southbound between Berry and Channel Streets.

As a response to community feedback, the project team developed a two-phase implementation of the temporary transit lanes to allow for an evaluation of their effectiveness before fully restricting northbound bridge traffic.

The initial evaluation of the first phase has been completed, and data shows that partial implementation was effective in allowing Muni trains to travel across the bridge with little delay.

Currently, northbound left turns are restricted from 4th Street onto Berry Street. The previous left turn pocket at that location was converted to a temporary transit lane, while northbound through-traffic continues to be allowed on the bridge. As the city emerges from the public health order to less restrictive tiers, SFMTA will perform an additional evaluation of the existing Phase 1 implementation. If that analysis determines that northbound private vehicle traffic on the bridge has begun to cause delays to the T Third, the single northbound lane will be restricted temporarily to transit only between Berry and Channel Streets as a second phase of the project.

Phase 1: Complete

Evaluation of this phase began after the T Third resumed service in late January:

  • A southbound temporary emergency transit lane was installed in one of the two southbound lanes on the 4th Street Bridge.
  • Northbound left turns are now temporarily prohibited from 4th Street onto Berry Street.
  • The left turn pocket in the northbound direction from 4th onto Berry Street was converted to a temporary transit lane.

Phase 2: If a change in emergency order tiers shows that traffic is causing transit delay on the 4th Street Bridge:

  • A northbound temporary transit-only lane will be installed in the sole northbound lane on the 4th Street Bridge.
  • Northbound traffic will not be permitted on the 4th Street Bridge, with these additional temporary restrictions:
  • Heading north on 4th Street at Channel, no through traffic onto the 4th Street Bridge (right or left turn required).
  • Heading east on Channel, no left turn onto the 4th Street Bridge.
  • Heading west on Channel, no right turn onto the 4th Street Bridge.
  • Southbound general traffic will continue to be permitted.

Evaluation of the phased approach

The Phase 1 evaluation included site visits and several weeks of monitoring traffic on and around the 4th Street Bridge. The chief metric was whether general traffic blocked trains on the shared northbound lane across the 4th Street Bridge. If northbound traffic blocked trains more than five percent of the time, the plan was to implement Phase 2. Periods of evaluation included morning, mid-day and afternoon/evening peak.

SFMTA also monitored train travel times using location data from T Third train tracking devices to identify when trains experienced the longest travel times on the 4th Street Bridge. Because this data showed few instances when trains were blocked by northbound traffic, SFMTA paused implementation of the second phase.

Initial Phase 1 evaluation results

The data demonstrated that Phase 1 was successful in decreasing transit delays and protecting trains from traffic congestion. With the temporary emergency transit lanes in place:

  • On average, overall transit delay decreased by 63 percent at 4th and Berry streets.
  • T Third trains are now 2.5 times more likely to travel through the 4th and Berry street intersection without having to stop at a red light.
  • When trains do encounter a red light, the average wait time for a green signal is 70 percent shorter.
  • With Phase 1 in place, T Third trains were delayed by traffic congestion less than one percent of the time.

Next steps

The ongoing evaluation of the project will include a community survey in mid-March as well as continued technical evaluation of the effectiveness of these temporary transit lanes.  A renewed technical evaluation will take place with the changing of tiers in the city’s emergency public heath order.