Metro-North announces full implementation of PTC on Harlem and Hudson Lines

March 18, 2020
The wayside installations now cover 189 routes miles across Metro-North as PTC progress continues.

As of March 14, Metro-North Railroad’s (Metro-North) full Harlem and Hudson Lines are operating in Positive Train Control (PTC), according to Metro-North President Cathy Rinaldi.

In Connecticut, crews simultaneously completed activating PTC wayside equipment on the eight miles of the New Canaan Branch. 

The completions put a total of 189 route miles into PTC functionality, which represents 68 percent of Metro-North's mileage.

“The activation of PTC along our entire Harlem and Hudson Lines and the New Canaan Branch demonstrates our swift and steady progress to meet our systemwide goals for the end of the year,” said Rinaldi. “Our team has been working diligently on this crucial initiative to ensure the safety of our system.”

Positive Train Control enhances train safety behind the scenes by eliminating the potential for human error to contribute to train-to-train collisions, trains traveling into zones where railroad employees are working on tracks or derailments caused by a train traveling too fast into a curve or into a misaligned switch.

The system uses a network of computers onboard trains and along the tracks that are in communication with a central control hub, sharing data on rail conditions in real time. Like roads, every stretch of track has a speed limit; lights at the railroad’s equivalent of intersections flash red and green to indicate when a train must stop or can proceed. If the PTC system detects that a train is operating too fast for a given stretch of track, or is at risk of passing a stop signal, the system automatically steps in to slow or stop the train, while alerting the train’s engineer that it is doing so.

PTC builds upon existing Metro-North systems such as in-cab signaling and automatic civil speed enforcement. These safety measures already offer some of the most substantial functions of PTC to Metro-North customers, according to the railroad.

Installations continue on the remaining 62 miles of the New Haven Line. Full implementation of PTC will be completed on Metro-North by the federally mandated deadline of Dec. 31, 2020, according to the railroad.